Illustrative case studyThe owners, events and outcome figures on this page are a modelled scenario, not a description of a real client or project. The plot facts are Nakheel's published figures for Island E (price and payment plan sheet and draft development controls, September 2026). Construction costs are drawn from published Dubai cost ranges. It shows how we would run a villa on an Island E plot, and what the numbers could look like.
AED 3.87mcost avoided against the first numbers on the table
AED 15.09mfinal account, against an approved budget of AED 15.64m (excluding the plot)
4 of 11weeks of extension of time agreed, against the contractor's claim
35 monthsfrom plot review to keys
Location
Island E, Dubai Islands (Nakheel)
Plot
Waterfront, 8,050 sq ft
Plot price
AED 17.6m (AED 2,188 per sq ft)
Permitted
Basement, ground and two floors; 12.5 m; FAR 0.97
House
7,800 sq ft above ground, 3,200 sq ft basement
Owners
A British family relocating from London
01Before the plot

The plot review: what the brochure doesn't say

The family are choosing between a beach plot at around AED 2,346 per sq ft and a waterfront plot at around AED 2,188, both on Nakheel's September 2026 price sheet. Plots on Island E are paid in seven instalments from booking to September 2029. Before they submit an expression of interest, we review both plots and the draft development controls.

  • Shoreline rules can tighten. The draft controls allow the rules along the shoreline to be tightened after marine assessments. On a beach plot that is a design risk the owners would carry. They choose the waterfront plot.
  • Draft is not final. The controls are finalised with the sale and purchase agreement. We list the points to confirm in writing before signing: how basement area is treated, setbacks, site coverage, any deadline to start or finish building, and when the plot will have roads and services.
  • The house the rules allow. A floor area ratio of 0.97 on 8,050 sq ft gives about 7,800 sq ft above ground, over ground and two upper floors within 12.5 m, plus a basement.
  • The real total. Plot, design, approvals, construction, landscaping and contingency come to about AED 33.2m before furniture. The owners go ahead knowing the whole number, not just the plot price.

The cash plan nobody else draws

The plot instalments do not stop when building starts. In this programme, construction runs through 2028 and 2029 while four plot payments are still due. The year of peak outgoings is 2028, at about AED 14.7m. The owners arrange their funding for that before they commit.

  • Plot instalments
  • Build, design and fees
0246810121416AED m2026: plot AED 3.52m, build and fees AED 0.05m, total AED 3.57m3.620262027: plot AED 4.93m, build and fees AED 0.80m, total AED 5.73m5.720272028: plot AED 4.58m, build and fees AED 10.08m, total AED 14.66m14.720282029: plot AED 4.58m, build and fees AED 4.16m, total AED 8.74m8.72029
Annual outgoings, AED millions. Plot payments follow Nakheel's published schedule; build costs follow a typical spend curve over the 19-month construction period.
YearPlot (AED m)Build and fees (AED m)Total (AED m)
20263.520.053.57
20274.930.805.73
20284.5810.0814.66
20294.584.168.74
Plot payment schedule
InstalmentShareAED m
Oct 202620%3.52
Mar 202715%2.64
Sep 202713%2.29
Mar 202813%2.29
Sep 202813%2.29
Mar 202913%2.29
Sep 202913%2.29
02Brief and budget

A wish list that didn't fit the plot

The family's first wish list comes to about 10,400 sq ft above ground: five bedroom suites, a guest suite, a gym, a cinema, staff quarters and a large kitchen and family room. The plot allows about 7,800.

Rather than cut rooms, we reorganise. The gym, cinema, staff quarters and plant move to a 3,200 sq ft basement, subject to how the final controls treat basement area. The guest suite becomes a flexible ground-floor room. Every room the family cares about stays, and the house fits the rules before an architect has drawn a line.

Then the budget, built from the bottom up: construction at a luxury rate per square foot for the house above ground, a separate rate for the basement with its dewatering and waterproofing, external works, design fees, authority fees and a 10% contingency held by the owners, not the contractor.

Approved budget, excluding plot and furnitureAED m
Main contract: structure, envelope, MEP and fit-out12.00
External works, pool and landscaping1.00
Design team, interior design and consultant of record1.04
Nakheel, authority and utility connection fees0.30
Contingency, held by the owners1.30
Total approved budget15.64

Eastbridge's own fee is not included in these figures; set it against the cost avoided shown at the end. Construction rates sit inside published 2025–26 ranges for luxury villas in Dubai (around AED 900 to 1,400 per sq ft). Design fees of about 8% sit inside the published 6–12% range for full design and engineering.

03The team

Choosing the architect on more than the fee

We shortlist three architects with villa experience and a registered consultant able to act as consultant of record. Their fee proposals look far apart until they are read side by side: one excludes interior coordination, another excludes the construction-stage duties of the consultant of record. Normalised, the gap closes to a few per cent.

The owners appoint the practice whose villas they like best and whose scope is complete, and appoint their interior designer at the same time, so joinery, lighting and services are designed together from the start. They live in London throughout the design stage; we run a fortnightly design meeting by video and a decision log they can read on their phones.

04Design to cost

The concept came back AED 2.3m over budget

The concept is beautiful. The cost plan puts it at about AED 17.9m against an approved AED 15.64m. Left alone, that gap would have surfaced at tender, when it is far more expensive to fix. Instead we run a value review with the architect and engineers.

ChangeSaving (AED m)
Structure
Simplified the structural grid so the cantilevered terrace no longer needed deep transfer beams. Same overhang, less steel and concrete.
0.65
Glazing
Kept the full-height sliding glass on the water elevation; standard high-performance frames elsewhere. The view from every main room is unchanged.
0.90
Stone
Imported stone where it is touched and seen: entrance, living floors and the pool surround. Porcelain in plant, staff and service areas.
0.50
Cooling and services
Heat-load calculation after the glazing change let the cooling plant drop a size. Smaller plant room, lower running costs.
0.25
Total designed out before tender2.30

None of these changes is visible from the garden or the water. The design goes to Nakheel's design review and then to permit, both submitted by the consultant of record, with the cost plan back on budget.

05Tender

The cheapest bid was the most expensive

Four contractors price the same drawings. On the headline numbers, Contractor A is AED 0.75m cheaper than the next lowest bid. Put on a like-for-like basis, adding back what each bid leaves out and correcting what each under-prices, it is the most expensive of the four.

  • Headline price
  • Normalised, like-for-like
02468101214AED mContractor A: headline AED 11.85m, normalised AED 13.90mContractor A11.8513.90Contractor B: headline AED 12.95m, normalised AED 13.05mContractor B12.9513.05Contractor C: headline AED 13.40m, normalised AED 13.40mContractor C13.4013.40Contractor D: headline AED 12.60m, normalised AED 13.35mContractor D12.6013.35
Main contract and external works, AED millions. Pre-tender estimate: AED 13.00m.
BidHeadlineNormalisedWhat we found
Contractor A11.8513.90Lowest headline price. Pool and landscaping excluded (AED 1.0m); provisional sums of AED 1.6m against AED 0.6m in other bids; 14-month programme no one could achieve.
Contractor B12.9513.05Complete scope, realistic 18-month programme, named site manager and MEP lead. Small allowance added for a missing pool plant item.
Contractor C13.4013.40Complete and well-presented. Simply the most expensive.
Contractor D12.6013.35Preliminaries priced for 12 months of site staff on an 18-month job; the shortfall would have come back as claims.

The owners appoint Contractor B. After clarification and negotiation the lump sum is agreed at AED 12.88m, with ground risk, programme and a named site team written into the contract, and the long-lead glazing ordered as an early package.

06Construction

Nineteen months on site

Every week the owners receive a photo update; every month, a written report with progress, the forecast final cost, the risks and the decisions they need to make. The moments that decide the final account look like this.

  1. Month 15

    Long-lead glazing

    The sliding glass for the water elevation has a 26-week lead time.

    Ordered as an early package straight after contract award, with drawings checked before production.

    Glazing arrives in time for the envelope; no knock-on delay to fit-out.

  2. Month 18

    Dewatering

    The contractor claims AED 640,000 for extra dewatering in the basement excavation.

    The ground investigation was issued with the tender and the contract put ground risk with the contractor. Only the extra 1.2 m of basement depth the owners added in month 17, for a wine store, is a genuine change.

    Agreed at AED 85,000.

  3. Month 20

    Owners' upgrades

    The owners want a larger kitchen and a better home automation system.

    Both priced by the contractor and checked before anything is instructed, with the time effect stated. The owners decide with the number in front of them.

    AED 410,000 approved from contingency, no delay.

  4. Month 24

    Valuation 9

    The monthly payment application claims AED 1.42m.

    Measured on site against the programme: façade cladding claimed as complete is 60% fixed, and loose materials are not yet protected on site.

    AED 1.11m recommended. The balance is paid the following month, once the work is done.

  5. Month 29

    Delay claim

    The contractor seeks an 11-week extension of time, citing late information and shamal winds.

    Records show joinery information from the interior designer was five weeks late, causing four weeks of critical delay. Wind days were within the contract allowance.

    Four weeks granted, with four weeks of time-related cost. The owners keep their right to delay damages beyond that.

The monthly report

One page the owners can read in five minutes, wherever they are. This is month 27.

Illustrative. Reports are tailored to each client.

07Handover

Keys, and nothing left to chase

Handover is planned from the start of construction. We walk the house room by room and system by system, witness the commissioning of the cooling, water, pool, lighting and security systems, and issue the snag list in sections as areas finish. Three hundred and twelve items are recorded; all are closed before the owners accept the house.

The handover file is complete on the day: completion certificate, as-built drawings, warranties, operation and maintenance manuals, test certificates, and a schedule of keys and codes. Retention is released only when the defects period ends with nothing outstanding.

08Outcome

The final account

Final account, excluding plot and furnitureAED m
Main contract and externals: agreed lump sum12.880
Owners' upgrades (kitchen, home automation)0.410
Dewatering: the genuine change only0.085
Design development and agreed site variations0.275
Extension of time: four weeks of time-related cost0.100
Design team, interior design and consultant of record1.040
Nakheel, authority and utility connection fees0.300
Total15.090

Against an approved budget of AED 15.64m, the house comes in AED 0.55m under, having used AED 0.75m of the AED 1.30m contingency, AED 0.41m of it on upgrades the owners chose. Handover is four weeks later than the original programme, exactly the extension agreed.

Where the difference came from

Cost avoided against the first numbers on the tableAED m
Design brought back to budget before tender2.30
Lowest headline bid avoided (normalised cost difference)0.85
Dewatering claim reduced to the genuine change0.56
Extension of time held to four weeks, not eleven0.16
Total3.87

The programme

  • Pre-construction stages
  • Construction
147101316192225283134MonthPlot review and EOI: months 1 to 1Plot review and EOIBrief, budget, team: months 1 to 3Brief, budget, teamConcept and scheme design: months 4 to 8Concept and scheme designNakheel design review: months 7 to 9Nakheel design reviewDetailed design and permit: months 9 to 13Detailed design and permitTender and contract: months 13 to 15Tender and contractConstruction: months 16 to 34ConstructionSnagging and handover: months 34 to 35Snagging and handoverPlot instalment, month 1Plot instalment, month 6Plot instalment, month 12Plot instalment, month 18Plot instalment, month 24Plot instalment, month 30Plot instalments
Months from the plot review in October 2026. Construction assumes site access from early 2028; on a new island, the programme moves with Nakheel's infrastructure dates.
09Method

How this case study was built

The plot size, price per square foot, payment schedule, floors, height limit and floor area ratio are Nakheel's published Island E figures (price and payment plan sheet and draft development control regulations, 24 September 2026). Construction rates sit within published Dubai ranges: Engel & Völkers (December 2025) and Real Estate Club Dubai. Design fees sit within the 6–12% range published by Optimal Engineering. The family, the contractors, the events and the outcome are invented to show how we work and how the numbers move. Nothing here is a forecast for a particular plot; for that, we carry out a plot review.

Buying on Island E?

Send us the plot number, or the plots you are choosing between. We will tell you what you can build and what it will really cost.