Stage payment plan: indicative schedule
Your inputs
Busiest month, likely (S-curve)
AED 529,540 Range AED 341,560 (even) to AED 670,320 (peaked)
With an advance of AED 512,000 and 10% retention, you pay AED 529,540 in the busiest month and have paid AED 4,859,250 by handover. AED 255,750 of retention is still held after handover until the end of the defects period.
| Key figures | Low (even) | Likely (S-curve) | High (peaked) |
|---|---|---|---|
| Busiest month | AED 341,560 in month 2 | AED 529,540 in month 6 | AED 670,320 in month 6 |
| Advance paid on signing | AED 512,000 | AED 512,000 | AED 512,000 |
| Paid by handover | AED 4,859,250 | AED 4,859,250 | AED 4,859,250 |
| Retention held after handover | AED 255,750 | AED 255,750 | AED 255,750 |
Payments month by month
| When | Work valued | Retention held back | Advance recovered | You pay | Paid to date | Retention held | Advance not yet recovered |
|---|---|---|---|---|---|---|---|
| Advance payment, on signing | – | – | – | AED 512,000 | AED 512,000 | – | AED 512,000 |
| Month 1 | AED 87,000 | AED 8,700 | AED 8,710 | AED 69,590 | AED 581,590 | AED 8,700 | AED 503,290 |
| Month 2 | AED 256,000 | AED 25,600 | AED 25,620 | AED 204,780 | AED 786,370 | AED 34,300 | AED 477,670 |
| Month 3 | AED 406,000 | AED 40,600 | AED 40,640 | AED 324,760 | AED 1,111,130 | AED 74,900 | AED 437,030 |
| Month 4 | AED 530,000 | AED 53,000 | AED 53,060 | AED 423,940 | AED 1,535,070 | AED 127,900 | AED 383,970 |
| Month 5 | AED 617,000 | AED 61,700 | AED 61,760 | AED 493,540 | AED 2,028,610 | AED 189,600 | AED 322,210 |
| Month 6 | AED 662,000 | AED 66,200 | AED 66,260 | AED 529,540 | AED 2,558,150 | AED 255,800 | AED 255,950 |
| Month 7 | AED 661,000 | AED 66,100 | AED 66,160 | AED 528,740 | AED 3,086,890 | AED 321,900 | AED 189,790 |
| Month 8 | AED 617,000 | AED 61,700 | AED 61,760 | AED 493,540 | AED 3,580,430 | AED 383,600 | AED 128,030 |
| Month 9 | AED 530,000 | AED 53,000 | AED 53,060 | AED 423,940 | AED 4,004,370 | AED 436,600 | AED 74,970 |
| Month 10 | AED 406,000 | AED 40,600 | AED 40,640 | AED 324,760 | AED 4,329,130 | AED 477,200 | AED 34,330 |
| Month 11 | AED 256,000 | AED 25,600 | AED 25,620 | AED 204,780 | AED 4,533,910 | AED 502,800 | AED 8,710 |
| Month 12 | AED 87,000 | AED 8,700 | AED 8,710 | AED 69,590 | AED 4,603,500 | AED 511,500 | AED 0 |
| Handover: half the retention released | – | – | – | AED 255,750 | AED 4,859,250 | AED 255,750 | AED 0 |
| End of the defects period (month 24): balance of retention released | – | – | – | AED 255,750 | AED 5,115,000 | AED 0 | AED 0 |
| Total | AED 5,115,000 | AED 511,500 | AED 512,000 | AED 5,115,000 |
Last reviewed: October 2026, by Philip Chapman
Showing the example below. Switch on JavaScript to change the inputs.
An illustration of a typical schedule, not your contract and not legal advice. Payment is shown in the month the work is valued; in practice certification and payment follow some weeks later. Excludes variations, VAT and fees. Sources and assumptions
Keep or discuss this result
Sources. Typical advance and retention percentages from Al Tamimi & Company and DLA Piper; the example contract sum from the Eastbridge cost calculator. Full sources, assumptions and method: eastbridgestrategicpartners.com/tools/stage-payment-planner/#sources
Eastbridge Strategic Partners · Client-side project management for private villas in Dubai and Abu Dhabi · philip@eastbridgestrategicpartners.com · +971 56 744 0057 · eastbridgestrategicpartners.com
How the schedule works
The short answer: on a typical villa contract you pay an advance on signing, then monthly payments for the work valued, less retention and less a share of the advance, then half the retention at handover and the rest when the defects period ends. The planner shows how much leaves your account each month, and how much of your money is in the contractor's hands before it has been earned.
- Advance. Al Tamimi & Company describes an advance payment of between 10% and 20%, depending on the nature of the project, as industry practice.[1] Under FIDIC contracts it is given in return for an advance payment guarantee. The planner recovers it from each monthly valuation in proportion to the work done, a simple and common approach; your contract may set a different recovery schedule.
- Monthly valuations. The contract sum spread over the build period on the pattern you choose. Each month's value is rounded to the nearest AED 1,000 and the last month takes the difference, so the months add up to the contract sum exactly.
- Retention. DLA Piper describes common UAE practice as 10% retention, with 5% released at handover and 5% after the defects liability period.[2] Under the FIDIC Red Book, the taking-over certificate releases the first half.[1] Retention is not required by UAE law; the percentage, any cap and the release dates are whatever your contract says.
- Build period. The example uses 12 months. Published estimates put villa construction at typically 12–18 months[3] or 8–14 months for the construction phase alone.[4]
The column "Advance not yet recovered" is your exposure: money paid ahead of the work. It falls as the advance is recovered, which is why the advance payment guarantee should reduce on the same schedule and stay valid until the last of it is recovered. Retention is the opposite: the contractor's money in your hands, which is why it gives you leverage at handover.
From the builder's side, the first month's valuation was always the one we watched most closely, because front-loading the early payments is the easiest way for a contractor to finance a job with the owner's money. A schedule like this one, agreed before signing, gives you something to check each payment application against. Our guide to villa construction contracts in the UAE covers retention, advance payment guarantees and bonds in more detail.
Questions
How much advance payment is normal on a UAE villa build?
How much retention is held on a construction contract in the UAE?
When is retention released?
Why does the busiest month matter?
Is this legal advice?
Sources
- Al Tamimi & Company, Highlights of the laws of the UAE, the PRC and the common law applicable to construction contracts, part 2 (2011). www.tamimi.com
- DLA Piper, Global Construction Bulletin: Security of payment, UAE (October 2025). www.dlapiper.com
- Optimal Engineering Consultants, Cost to build a villa in Dubai (2026 guide, March 2026). www.optimal.ae
- Real Estate Club Dubai (property information website), Villa architects in Dubai: FF&E, approvals and timelines. realestateclubdubai.com
Rates last reviewed October 2026 by Philip Chapman. This page gives general information, not financial, legal or engineering advice.
Other tools
- Villa build and renovation cost calculatorLow, likely and high costs with fees, approvals, contingency and a timeline.
- Renovate or rebuild?Renovation against knock-down-and-rebuild, per sq ft of finished space.
- Delay cost estimatorWhat each month of delay costs an owner.
- All toolsFree planning tools for villa owners, each with its sources.
Want a second pair of eyes on the numbers?
Philip replies personally within one working day. The first conversation is free. Nothing you send is published, and it is shared only with the service providers named in our privacy notice.