Key points

  • A developer handover is a different exercise from a private build. You did not appoint the contractor, you hold no retention, and the developer's process, not your contract, sets the order of events.
  • Your leverage is the snag inspection before you accept the villa, and the written record you keep afterwards. Report every defect in writing; Emaar's defects cover, for example, excludes items not reported in writing within the warranty time frames.
  • Under Dubai Law No. 6 of 2019, a developer of jointly owned property is liable for structural parts for 10 years from the completion certificate and for installations for 1 year from handover. Developers' own defects periods vary; Emaar's runs for 1 year from snag completion or the contract completion date, whichever is later.
  • Test the systems before you look at the finishes: water ingress, air conditioning, drainage, hot water and electrics cause most of the expensive problems, and they are the easiest to miss on a short walk-round.

Taking the keys to a new villa from a developer feels like the end of the process. For the condition of the house, it is closer to the beginning. Once you accept the villa, everything you find afterwards has to be chased through the developer's service request process, and some of it will be argued about.

This guide is for owners buying a completed or off-plan villa from a Dubai developer. If you are building your own villa with your own contractor, the process and your leverage are different; our new villa snagging checklist covers that case.

Why is a developer handover different?

On a private build, you appoint the contractor, the contract sets the handover process, and you usually hold retention and a final payment until the snags are closed. On a developer villa, none of that applies:

  • You did not appoint the contractor and you have no contract with it. Your agreement is with the developer.
  • There is usually no retention. You will normally have paid the final instalment and service charges before you can take possession.
  • The developer's process sets the order. Emaar's 2025 handover fact sheet, for example, lists settling outstanding payments, receiving a certificate of completion of payment, paying the DEWA security deposit, completing land registration and then attending handover.

That leaves you with two kinds of leverage: the inspection before you accept the villa, and the written record you keep afterwards. Both need to be done properly.

Aerial render of villas around a landscaped lake at Address Villas Hillcrest, Dubai Hills Estate
Dubai Hills Estate, for illustration. Image: Emaar.

What does the law and the developer cover?

There are two layers, and they are often confused.

Cover What it applies to How long Source
Developer's statutory liability (structure) Structural parts of jointly owned property 10 years from the completion certificate Dubai Law No. 6 of 2019, Article 40
Developer's statutory liability (installations) Installations such as electrical, plumbing and mechanical 1 year from handover Dubai Law No. 6 of 2019, Article 40
Developer's defects period (example: Emaar) Electrical, plumbing and cooling systems; cladding; caulking, windows and doors where water gets in 1 year from snag completion or the contract completion date, whichever is later Emaar Community Management DLP factsheet

Each developer runs its own defects process, so read yours. The Emaar factsheet also lists exclusions, including work supplied by the purchaser or its contractors, normal wear and tear, improper maintenance or misuse, drain blockages not caused by construction debris, cosmetic damage after orientation, and items not reported in writing within the warranty time frames. That last exclusion is the one owners most often fall foul of.

Take advice from a UAE-qualified lawyer on how these rules apply to your villa and your sale and purchase agreement.

The 20 items we check first

From the contractor's side, I know which parts of a house get finished last and checked least: the ones behind a ceiling, under a tile or on the roof. A snag list full of paint marks and missing silicone can look thorough while missing the problems that cost real money. So we start with the systems and the building envelope, then move to finishes.

# Item What we do Why it matters
1 Roof and terrace waterproofing Look at falls, outlets and upstands; water test where allowed Leaks show months later, inside
2 Wet room floors Flood test showers and check falls to drains Water under tiles damages the room below
3 Windows and doors Check seals, drainage slots, locking and alignment; hose test where allowed Water and dust ingress, AC losses
4 External walls and cladding Look for cracks, open joints and failed sealant The developer cover names cladding and water entry
5 Air conditioning Run every unit; check supply temperature, noise and condensate drainage The most expensive system to get wrong in Dubai
6 AC access Confirm every unit, filter and valve can be reached for servicing Poor access costs money every service
7 Hot water Run hot water at every outlet; check heater, pressure and recovery time Faults show only under use
8 Drainage Run water at every outlet and check for slow drains and smells Blockages from construction debris are covered; later ones may not be
9 Electrical distribution board Check labelling, test the residual current devices, look for heat Safety, and evidence for later claims
10 Sockets and lighting Test every socket, switch and fitting Quick to do and easy to forget
11 Moisture readings Check walls and floors near wet rooms, roofs and external doors Finds leaks before they stain
12 Thermal imaging Look for missing insulation, hot spots and hidden leaks Shows what the eye cannot
13 Pool (if fitted) Run the plant, check for leaks, test lighting and safety features Pool plant faults are costly to trace
14 Kitchen Test every appliance, check worktop joints, sealing and extraction Warranties start at handover
15 Joinery and wardrobes Check doors, hinges, alignment and soft-close fittings Easier to fix before you move in
16 Floor finishes Look for hollow tiles, lippage, cracks and damaged stone Hollow tiles can crack later
17 Walls and ceilings Check for cracks, uneven finishes and patched areas Patches can hide services work
18 External areas Check paving falls, boundary walls, gates and garden irrigation Ponding water and failed gates are common
19 Smart home and security Test access control, cameras, intercom and any home automation Systems often need setting up and handing over
20 Paperwork Collect warranties, drawings and manuals; check meter readings Your evidence if you need to claim later

On a villa, items 1 to 12 usually matter more than the rest put together.

What paperwork should you collect?

Emaar's fact sheet says a villa handover includes keys, a USB with warranty details, drawings, community rules and important contact numbers. Whatever your developer provides, make sure you leave with:

  • the keys and access cards for every door and gate, counted and listed;
  • warranties for appliances, AC and any pool or specialist equipment;
  • drawings, ideally showing services routes, which you will need for any later renovation;
  • operation and maintenance information for the AC, water heating, pool and smart systems;
  • meter readings on the day, photographed;
  • your snag list, signed or acknowledged, with a reference number and an agreed date for each item.

If something is missing, write it on the list rather than accepting a promise to send it later.

Render of two-storey villas on a palm-lined road at Golf Place II, Dubai Hills Estate
Dubai Hills Estate, for illustration. Image: Emaar.

How do you keep the snag list moving?

Most snag lists stall after handover. In our experience, the ones that get closed share a few habits:

  1. Report everything in writing, through the developer's service request route, and keep every reference number.
  2. Photograph each item with a wide shot that shows where it is and a close-up that shows the defect.
  3. Agree dates for each item and follow up when they pass.
  4. Re-inspect after the developer says items are closed. Do not sign them off from a message.
  5. Diarise the end of the defects period and do a full inspection a month or two before it, so anything new is reported in time.

Avoid starting your own alterations before the snags are closed. If your contractor works on an area with an open defect, the developer may say the problem is now yours. Our defects liability period guide covers the first year in more detail, and the owner site visits guide explains what to record when you walk a house.

How Eastbridge can help

We inspect developer villas before you accept them, starting with the systems and envelope items above, and give you a written snag report with photographs, priorities and the paperwork to collect. We then track the snag list with you through the developer's process and re-inspect before items are signed off. If you are overseas, we can carry out the inspection and report to you; attending the handover itself needs the owner or someone holding a properly attested power of attorney, as the developer's rules set out. Our snagging and handover service sets out what is included, and you can contact us to arrange an inspection.

Philip Chapman, Founding PartnerFounded and ran P Chapman Construction, a UK builder of award-winning homes, for 21 years. Now represents villa owners in Dubai and Abu Dhabi. About Philip

Questions

Can I refuse to accept a developer villa because of snags?
That depends on your sale and purchase agreement and the developer's handover process. In practice, most buyers record the snags, agree a timetable for fixing them and accept the keys, rather than refusing handover. Read the agreement first, and take advice from a UAE-qualified lawyer if the defects are serious enough to make the villa unusable.
How long is a Dubai developer liable for defects in a new villa?
For jointly owned property, Dubai Law No. 6 of 2019 makes the developer liable for structural parts for 10 years from the completion certificate and for installations for 1 year from handover. Each developer also sets its own defects process. Emaar's factsheet, for example, describes a 1-year defect liability period from snag completion or the contract completion date, whichever is later.
Should I snag the villa myself or hire someone?
You can do a first pass with a checklist, but water testing, moisture readings, thermal imaging and AC performance checks need the right equipment and some experience. On a villa, the value is in finding the hidden problems, not the scuffed paint.
What happens to snags found after I take the keys?
Report them to the developer in writing through its service request process, keep the reference numbers and photographs, and follow up within the defects period. Items not reported in writing within the warranty time frames may not be covered.

Sources

  1. Dubai Law No. 6 of 2019 concerning Ownership of Jointly Owned Real Property, Article 40 (Dubai Legislation Portal)
  2. Emaar Community Management: handover fact sheet 2025
  3. Emaar Community Management: defect liability period factsheet
  4. Legal 500: understanding developer liability for maintenance and defect costs after property handover

This article is general information, not advice for your specific project. Figures are from the sources cited and change over time.

Philip Chapman's record

Built by our founder in the UK

UK work by P Chapman Construction, the company Philip founded and led for 21 years. See the work

The Lookout, Mylor, Cornwall
The Lookout, Mylor, Cornwall
Menwinnion, Mylor Churchtown, Cornwall
Menwinnion, Mylor Churchtown, Cornwall
Saqqara, Feock, Cornwall
Saqqara, Feock, Cornwall
Image: Emaar